Harvey Stern records, enforces and defends against mechanics liens, stop payment notices and payment bond claims throughout Los Angeles County. For contractors, subcontractors and suppliers: preliminary notices, timely recording, and the foreclosure lawsuit that must follow within 90 days. For owners: verifying whether a lien is valid, petitions to release defective liens under Civil Code section 8480, lien release bonds, and recovering attorney's fees when a lien should never have been recorded.
The deadlines that decide lien cases
California's mechanics lien law (Civil Code sections 8000 to 9566) is a sequence of short deadlines, and missing any one of them ends the claim.
- Preliminary notice. Subcontractors and suppliers must serve a preliminary notice within 20 days of first furnishing labor or materials (section 8200 and following). A direct contractor must serve it on the construction lender. Without it, the lien and stop notice rights are lost for work before the notice.
- Recording. A direct contractor must record the lien within 90 days after completion of the work of improvement, or within 60 days after the owner records a notice of completion or cessation (section 8412). Subcontractors and suppliers have 90 days after completion, or 30 days after a notice of completion (section 8414). "Completion" has its own definition, and arguing about the date is a large part of lien litigation.
- Foreclosure. A lawsuit to foreclose the lien must be filed within 90 days after the lien is recorded (section 8460), or the lien is void. An extension of credit can be recorded, but the rules are strict.
- Amount. The lien is limited to the reasonable value of the work provided or the contract price, whichever is less (section 8430). Overstated liens expose the claimant to forfeiture and fees.
For contractors, subcontractors and suppliers
The firm prepares and serves preliminary notices, records liens with the Los Angeles County Registrar-Recorder, serves stop payment notices on lenders, and files the foreclosure action in Los Angeles Superior Court. Harvey has been on the contractor's side of a non-paying owner and knows that the lien is leverage, not an end in itself; the objective is payment, and a well-timed lien with a credible foreclosure complaint behind it usually produces it. Payment bond claims on public and private projects, and the prompt-payment penalties under Business and Professions Code section 7108.5 and Civil Code section 8800 and following, are part of the same toolkit.
For property owners
A lien on title blocks a sale or refinance and clouds everything. Many liens recorded in Los Angeles are defective: no preliminary notice, recorded late, overstated, recorded by an unlicensed contractor (who has no lien rights at all under Business and Professions Code section 7031), or never followed by a lawsuit. The firm reviews the lien and the project history and chooses among the remedies: a demand for release, a petition to release the lien under Civil Code section 8480 (with attorney's fees to the prevailing party under section 8488), a lien release bond under section 8424 to clear title while the dispute continues, or a defense of the foreclosure action on the merits and the underlying contract.
Preventing lien problems
Owners can protect themselves by requiring conditional and unconditional lien releases (sections 8132 to 8138) with every progress payment, checking preliminary notices against the pay applications, and recording a notice of completion promptly to shorten the lien window. Contractors protect themselves by serving preliminary notices on every job, calendaring completion, and never letting a 90-day period pass without a decision. The firm sets these systems up for clients who build or own regularly.
Frequently asked questions
How long does a contractor have to file a mechanics lien in California?
A direct contractor must record within 90 days after the work of improvement is completed, or within 60 days after the owner records a notice of completion or cessation. Subcontractors and suppliers have 90 days after completion or 30 days after a notice of completion. The claimant then has 90 days after recording to file a lawsuit to foreclose the lien, or it expires.
How do I remove a mechanics lien from my property?
If no foreclosure lawsuit was filed within 90 days of recording, the lien is void and the claimant must release it; if it refuses, a petition under Civil Code section 8480 gets a court order and attorney's fees. If the lien is defective for another reason (no preliminary notice, unlicensed claimant, overstated amount), the same petition or a demand usually works. If you need title clear immediately, a lien release bond under section 8424 substitutes the bond for the property while the dispute is resolved.
Can I file a lien if I did not send a preliminary notice?
A direct contractor with a contract with the owner does not need to serve a preliminary notice on the owner, but must serve one on any construction lender. Subcontractors and suppliers must serve the notice within 20 days of first furnishing; serving it late preserves lien rights only for work in the 20 days before service and afterward. If the notice was missed entirely, there may still be a contract claim against whoever hired you, but the lien is usually gone.
What is a stop payment notice?
A stop payment notice is served on the construction lender (or on the owner on a public work) and requires it to withhold funds for the claimant's benefit. It is often more effective than a lien on a financed project because it reaches money that has not yet been disbursed. The deadlines mirror the lien deadlines, and a bonded stop notice gives the claimant priority over the lender.