In California, a direct contractor must record a mechanics lien within 90 days after completion of the work of improvement, or within 60 days after the owner records a notice of completion or cessation. Subcontractors and suppliers have 90 days after completion or 30 days after a notice of completion, and must have served a preliminary notice within 20 days of first furnishing labor or materials. A lawsuit to foreclose the lien must be filed within 90 days after the lien is recorded, or the lien expires.
The timeline
| Step | Who | Deadline | Statute |
|---|---|---|---|
| Preliminary notice | Subcontractors, suppliers, equipment lessors; direct contractor to lender | Within 20 days of first furnishing (late notice covers only the prior 20 days and after) | Civil Code §§ 8200–8216 |
| Record the lien | Direct contractor | 90 days after completion, or 60 days after a notice of completion or cessation is recorded | § 8412 |
| Record the lien | Subcontractors and suppliers | 90 days after completion, or 30 days after a notice of completion or cessation | § 8414 |
| Serve the lien on the owner | All claimants | Before or at recording, with the statutory Notice of Mechanics Lien | § 8416 |
| File the foreclosure lawsuit | All claimants | 90 days after the lien is recorded | § 8460 |
| Record a lis pendens | Claimant | Promptly after filing suit | § 8461 |
| Petition to release a stale lien | Owner | Any time after the 90-day foreclosure period passes without suit | §§ 8480–8488 |
What "completion" means
The lien recording deadlines run from completion of the work of improvement, which Civil Code section 8180 defines as actual completion, occupation or use by the owner accompanied by cessation of labor, cessation of labor for a continuous 60 days, or recording of a notice of cessation after 30 days of no work. On a remodel, "completion" is often a disputed date, and the dispute decides whether the lien was timely. Keep records of the last day labor was furnished.
The notice of completion
An owner who records a notice of completion within 15 days after actual completion (section 8182) shortens the lien window to 60 days for the direct contractor and 30 days for everyone else. The notice must be served on the direct contractor and on every claimant who served a preliminary notice. It is one of the cheapest protections an owner has and it is rarely used on residential projects.
After the lien is recorded
The claimant has 90 days to file a foreclosure action in Superior Court and should record a lis pendens when it does. A lien with no lawsuit after 90 days is unenforceable; the owner can demand a release and, if the claimant refuses, petition the court under section 8480 for an order releasing it, with attorney's fees to the prevailing party under section 8488. An owner who needs clear title immediately can record a lien release bond for 125 percent of the lien amount under section 8424, which moves the dispute from the property to the bond.
Other claims that run on the same clock
Stop payment notices to a construction lender (sections 8500 and following) and payment bond claims have deadlines that mirror the lien deadlines. Contractors on financed projects should use all three. The firm's mechanics lien page explains how it handles each for contractors and for owners.
Related questions
What happens if a contractor misses the 90-day deadline to record a lien?
The lien right is lost. The contractor may still sue the party it contracted with for breach of contract, but it cannot encumber the property, and it loses the leverage and the attorney's fee and priority advantages that the lien provides.
Can a lien be recorded on my home for work I did not authorize, such as work ordered by a tenant?
An owner who learns of unauthorized work can record and post a notice of non-responsibility under Civil Code section 8444 within 10 days of learning of it, which protects the owner's interest from liens for that work. Without the notice, the owner's interest may be liened if the owner knew of the work.
Does an unlicensed contractor have lien rights?
No. A contractor that was not properly licensed throughout the work cannot record an enforceable lien and cannot sue to collect, under Business and Professions Code section 7031. An owner faced with a lien from an unlicensed contractor can have it released.
This article is general information about California law, not legal advice for your situation. Facts matter; deadlines run. For advice on your own matter, request a free consultation.